Western Standard - September 17, 2024


Dreeshen Alberta to Build Proper Calgary Green Line


Episode Stats

Length

5 minutes

Words per Minute

166.79779

Word Count

848

Sentence Count

44


Summary

Calgary's Green Line project has been in the news lately, and there's a lot of misinformation about it. So let's set the record straight. To understand the Green Line, we first need to take a look at the history of the project, and exactly how it is that we got where we're at today.


Transcript

00:00:00.320 There's been a lot of talk about Calgary's Green Line project lately and
00:00:03.600 unfortunately a lot of misinformation as well. So let's set the record straight.
00:00:09.200 To understand the Green Line we first need to take a look at the history of the project and
00:00:13.760 how it started and exactly how it is that we got where we're at here today.
00:00:18.480 The Green Line was first introduced in 2015 by Nahid Nenshi when he was the Mayor of Calgary.
00:00:24.720 It was promised to be a 46 kilometer line that would run from 160th Ave North
00:00:29.600 all the way to Seton at the south end of the city and include 29 stations.
00:00:34.560 The project was also supposed to include a tunnel running under the Bow River and through the
00:00:39.520 downtown core. Back then this mega project was going to cost $4.65 billion. The only issue the
00:00:46.800 City Council back then failed to do any of the proper costing, engineering or planning before
00:00:52.560 coming up with that $4.65 billion price tag. At best it was drawn up on a napkin.
00:00:59.120 Now as you could probably imagine that's not how competent or responsible organizations build
00:01:04.640 large and complex mega projects like this one. It's impossible to determine how much any project
00:01:11.360 will actually cost if you don't plan, design and engineer it beforehand. So it didn't take long for
00:01:17.200 the Green Line project to start falling off the rails. Under the previous government in 2017, the Green Line
00:01:24.000 was slashed from the original 46 kilometers and 29 stations to only 23 kilometers and 15 stations.
00:01:30.640 The City also abandoned the entire north side of the Green Line. Now this alignment was done to make the
00:01:36.800 budget fit inside an over-promised and poorly planned project design. But the shrinking of the Green Line
00:01:43.120 didn't stop there. Even after cutting it by half of the original size, the Green Line project was
00:01:48.800 facing massive cost overruns. Calgary City Council was still finding it impossible to build the project
00:01:55.440 with a $4.65 billion budget. So they cut it down to 18 kilometers, abandoning any stations north of the
00:02:01.840 Bow and only going as far south as Sheppard. But they kept the big expensive tunnel under downtown which
00:02:08.240 was responsible for the majority of the costs. Unfortunately, even with these further cost-saving
00:02:14.160 measures, the Green Line could still not be built. And so the City shrunk the Green Line even further
00:02:20.720 and reduced the Green Line scope down to only 10 kilometers and seven stations running from Eau Claire to
00:02:27.120 the Linwood Millican station in the southeast. So from an original lack of planning, the Green Line
00:02:31.760 shrunk from 46 kilometers and 29 stations that Calgarians were promised almost 10 years ago down
00:02:37.840 to just 10 kilometers and seven stations. Now this just goes from bad to worse. The most recent 10
00:02:43.920 kilometer mini version of the Green Line doesn't serve a lot of Calgarians at all. And the project costs
00:02:48.720 have now, brace yourselves, gone up to $6.2 billion. Now to put that into perspective, that means that
00:02:56.160 taxpayers will be paying $630 million for each kilometer of track. Now that's just ridiculous.
00:03:02.480 For example, Montreal's REM line only costs around $86 million per kilometer or seven times less than
00:03:08.560 this current Green Line. Now this new alignment would make the Green Line one of the most expensive
00:03:13.600 and least effective LRT projects in North America. And all this taxpayer money, while Calgarians need to
00:03:20.880 build a new water line to ensure this summer's water crisis isn't repeated. And unfortunately,
00:03:26.160 lack of poor water infrastructure has been a decade-long issue, but that's for another day.
00:03:31.440 Now as your provincial government, we have an obligation to ensure taxpayers' dollars for
00:03:35.760 infrastructure are spent efficiently, responsibly, and in a way that benefits the most amount of
00:03:41.120 Albertans possible. We are not going to throw billions of taxpayer dollars away on a vanity project
00:03:47.920 that fails in every way to address the actual transit needs of Calgarians. This is why we are
00:03:53.840 taking immediate action to fix this nightmare. We will be working with experienced engineers to design
00:04:01.120 a new above-ground Green Line alignment that integrates with the Red and Blue Lines, connects
00:04:06.800 to the future Grand Central Station at Calgary's new Arena Entertainment District, and then stretches
00:04:12.240 south to the community of Shepherd and beyond. We also have big plans for the City of Calgary
00:04:17.680 and for the province when it comes to passenger rail, and we are going to deliver on them in a way
00:04:23.680 that respects the hard work and investment of our taxpayers. This government finished Calgary's
00:04:30.480 Ring Road on time and on budget, and we're adding lanes to the Deerfoot to help Calgarians spend less
00:04:36.640 time in traffic and more time at home doing the things that they love. We want to improve the quality
00:04:43.040 of life for Calgarians, and we're committed to work with this City Council to deliver a Green Line
00:04:49.520 that actually goes somewhere, and that Calgarians can be proud of. Thank you and we'll see you around.